Home

Construction RFP Template: Scope, Safety Requirements, and Bid Evaluation

A complete construction RFP template with safety requirements, bonding and insurance specifications, CSI MasterFormat scope definitions, and evaluation criteria that balance cost with quality and safety.

Construction RFP vs. Invitation to Bid (ITB)

Use an RFP When...

  • Design-build projects where the contractor contributes to design decisions
  • Complex projects requiring value engineering
  • Projects where safety record and methodology matter as much as price
  • Negotiated contracts where best-value selection is appropriate

Use an ITB When...

  • Complete plans and specifications are available (bid-spec projects)
  • Price is the primary selection criterion
  • Government projects requiring low-bid award
  • Standard, well-defined scope with minimal design input needed from contractors

Construction-Specific RFP Sections

Scope of Work (CSI MasterFormat)

Define scope using CSI MasterFormat divisions for clarity. Key divisions: Division 03 (Concrete), Division 05 (Metals), Division 06 (Wood/Plastics), Division 07 (Thermal/Moisture Protection), Division 08 (Openings), Division 09 (Finishes), Division 22 (Plumbing), Division 23 (HVAC), Division 26 (Electrical), Division 28 (Fire Protection). Specify which divisions are in scope, whether the contractor provides materials or owner-furnished contractor-installed (OFCI), and any specific product or finish selections.

Safety Requirements

Require: Experience Modification Rate (EMR) below 1.0 for the last 3 years (EMR above 1.0 indicates worse-than-average safety performance), OSHA 300 log for 3 years, site-specific safety plan before mobilization, designated safety officer for projects above $500K, weekly toolbox talks documentation, and drug testing program. Construction has the highest fatality rate of any industry. Safety requirements are not optional.

Bonding Requirements

Standard bonding for construction RFPs: Bid Bond (5% of bid amount, ensures the contractor will honor their bid price), Performance Bond (100% of contract value, protects against contractor default), Payment Bond (100% of contract value, protects subcontractors and suppliers). For public projects, the Miller Act requires performance and payment bonds on federal contracts above $150,000. Most states have similar requirements.

Insurance Minimums

Standard construction insurance requirements by project value: Projects under $500K require $1M general liability and $1M auto liability. Projects $500K to $2M require $2M general liability, $5M umbrella. Projects above $2M require $5M general liability, $10M umbrella. All projects require workers' compensation at statutory limits and professional liability of $1M minimum for design-build.

Schedule Requirements

Require a CPM (Critical Path Method) schedule or Gantt chart with: milestone dates, submittals schedule, inspection dates, weather contingency days, liquidated damages for late completion (typically $500 to $2,000 per calendar day depending on project size), and the process for schedule extensions due to owner-caused delays or force majeure.

Change Order Process

Define: how change orders are initiated (written request only), markup percentages (typically 10% to 15% overhead and profit on change orders), documentation requirements (time and materials backup), approval authority levels, and the process for disputed change orders. Construction projects average 10% to 15% change order volume. A clear process prevents disputes.

Bid Evaluation for Construction

Unlike professional services RFPs, construction bids have the widest cost variance of any industry, often 30% to 50% between the highest and lowest bidder. This makes evaluation criteria especially important. Selecting the lowest bidder without evaluating safety, schedule, and quality often leads to cost overruns that exceed the original savings.

CriterionWeightWhat Evaluators Check
Cost and Value Engineering25%Total bid price, unit prices, allowances, alternates, value engineering suggestions
Technical Approach and Schedule25%CPM schedule feasibility, crew size, equipment plan, phasing approach, weather contingency
Safety Record and Compliance20%EMR rating trend, OSHA citations, site safety plan quality, designated safety officer
Experience and References20%Similar completed projects (size, type, location), client references, team qualifications
Warranty and Quality Assurance10%Warranty terms, QA/QC plan, inspection schedule, defect correction process

Contractor Pre-Qualification Questionnaire

For projects above $500K, pre-qualify contractors before issuing the RFP. This ensures you only send the RFP to contractors capable of performing the work, reducing evaluation effort and improving proposal quality.

1

Company legal name, address, and years in business

2

Annual revenue for the last 3 fiscal years

3

Current bonding capacity and bonding company name

4

Insurance certificates with current limits

5

EMR rating for the last 3 years

6

OSHA 300 log for the last 3 years

7

List of 5 similar projects completed in the last 5 years (project name, owner, value, completion date)

8

3 owner references with contact information

9

Key personnel: project manager, superintendent, safety officer (names and resumes)

10

Current backlog (total dollar value of work under contract)

11

Subcontractor management approach (self-perform percentage, key subcontractor relationships)

12

Litigation history for the last 5 years (any claims, disputes, or judgments)

13

Any OSHA citations in the last 3 years (describe and provide resolution)

Next Steps